Skip Global Navigation and Quick Links or Go to Global Navigation or Go to Quick Links
Transportation & Engineering
100 Jefferson County Pkwy, Ste. 3500
Golden, CO 80419
303-271-8495

by  
Go to H & T Navigation


 

Welcome to Jefferson County Transportation & Engineering Department.

Project Hall of Fame

Summary of Projects Recently Completed

 Roadway Projects  Drainage Projects


Crawford Gulch Bridge on Golden Gate Canyon Road - 2006 

  


CrawfordGulchBridge Before Construction

Project Scope:
  The old bridge was rated "very low" by CDOT's bridge sufficiency rating system.  It was replaced with a reinforced concrete box culvert bridge.  The design allowed the existing rock abutment walls to stay in place, which reduced construction time. The new bridge includes two 12-foot lanes with four-foot shoulders, extra width for a future right-turn lane onto Crawford Gulch Road (if needed), and guardrail.
As construction begins...
Crawford Gulch Bridge (as construction is completed)
As construction is completed...
    
   Crawford Gulch construction
               Construction wing walls...

 

 

 

 

 

 

 

 

 

 

 

 



 


 McIntyre Street, State Highway 58 to Croke Canal - 2007

Project Scope:  Increases in traffic volume warranted a larger intersection with dedicated left turn lanes and safer pedestrian crossings. Therefore, the existing two-lane street was widened to four through lanes, with left-turn lanes and acceleration/deceleration lanes, and sidewalks. A pedestrian bridge over the Croke Canal and storm sewer were included in the plans, by Muller Engineering. The $4 million project was funded by the county Road & Bridge Fund and the North Plains Impact Fees.

McIntrye before construction
Before construction...


McIntyre and 44th intersection after construction
After completion of intersection...


McIntrye completed project
After construction...










 

 

 

 

 

 

 

 

 

 

 


Massey Draw Stabilization - 2007 

 Massey Draw completed project
Completed construction...

Project Scope:  During a large storm event in June 2004, Massey Draw experienced significant erosion, including parts of adjacent residential backyards.  This project stabilized the channel near Massey Circle and Allison Street by constructing boulder walls, drop structures and bank stabilization.


The plans, by Muller Engineering, inlcuded a 20-foot-wide channel with boulder wall sides.  Drop structures, which flatten the channel slope, minimize erosion and encourage new plant growth.  The $400,000 project was funded 50/50 by Urban Drainage & Flood Control District (UDFCD) and the Jefferson County General fund.  Massey Draw completed project
Another view of completed project...



Lakewood Gulch Stabilization in Welchester Tree Grant Park


Project Scope:  Over time, Lakewood gulch has eroded, posing a hazard to the safety of park users and children that pass through the park on their way to Welchester Elementary School.  In some areas the banks are undercut 15 feet deep. The stream will be stabilized through a series of drop structures constructed to slow stream flows and reduce erosion.  Vegetation lost during construction will be replaced with smaller stock.  The $300,000 project was funded 50/50 by Urban Drainage & Flood Control District (UDFCD) and Jefferson County General Fund.  Lakewood Gulch Welchester
Completed project...
 Lakewood Gulch Welchester-2
Another view of the completed project...
Construction Schedule:  Construction was completed in the summer of 2007.
Landscaping will be completed in spring 2008.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 


 What's a Rumble Strip?

Rumble strips are grooves in asphalt pavement that are milled-in perpendicular to the direction of travel to alert inattentive drivers.  As a vehicle passes over the rumble strips, noise and vibration are produced, alerting the driver they are approaching a hazard.  There are two main types of rumble strips.  First, ?Shoulder Rumble Strips? are placed at the outermost edge of the paved surface to warn motorists their vehicle is entering a part of the roadway not intended for routine traffic use.  Second, ?Centerline Rumble Strips? are placed on the centerline of undivided highways to warn drivers they are leaving their intended lane of travel.  Centerline rumble strips have been demonstrated to reduce head-on and opposing direction sideswipe crashes.  In addition, drivers tend to slow down when approaching curves of winding mountain roads.

 Grinding Machine at Work
Grinding machine at work...

 

 

 

 

 

 

 

 

 





Recently, the Highways & Transportation Division completed almost 18 miles of centerline rumble strip installations on six roads in the Conifer, Evergreen and Ken Caryl area as part of the 2007 traffic safety improvements program.  Surface Preparation Technologies, Inc. out of Pennsylvania was contracted to grind the rumble strip pattern using their customized equipment.  Traffic delays were reduced to only a few minutes because the entire grinding operation moved at a regular walking pace.  That way, traffic flaggers walking in front and behind the grinding equipment were able to safely route vehicles around the operations in controlled waves.  Asphalt millings from the grinding operations will be re-used by the county Road & Bridge Division for maintenance.

The road segments that received centerline rumble strips are:
1) Ken Caryl Avenue between Valley Parkway and Valley Road;
2) Deer Creek Canyon Road between Owens Street and S. Deer Creek Road;
3) Pleasant Park Road between US 285 and Oelmann Park  Road;
4) North Turkey Creek Road between US 285 and High Drive;
5) Brook Forest Road between County Road 73 and Black Mountain Drive; and
6) County Road 73 between State Highway 74 and Wonderview Avenue.

Jefferson County now has almost 40 miles of roads with centerline rumble strips.  The other roads include Deer Creek Canyon Road between S. Deer Creek Road and S. Turkey Creek Road, and Golden Gate Canyon Road from the Road & Bridge Central Shop to the county line.  The public reaction to the centerline rumble strips has been mostly positive.  Several drivers have recounted their experiences of drifting over the centerline at night or in snowy conditions and being alerted by the noise.  In other cases, bicyclists riding along the shoulder of the road appreciate the centerline rumble strips because they hear vehicles approaching from behind them. 

Back to Top


Cooper Drive Reconstruction

Project Scope:   Due to the heaving soils typically found in the Ken Caryl area of Jefferson County, a segment of Cooper Drive, from West Coal Mine Drive to approximately 500 feet to the northwest, required reconstruction.  Varying moisture content in clay soils caused the pavement, curb, gutter and sidewalk on Cooper Drive to heave (rise) up, creating bumpy driving/walking conditions.  Cooper Dr. prior to reconstruction
 
 
 
 
 
 

 

To help prevent the moisture problem and future heaving, the pavement, curb, gutter, and sidewalk was removed and reconstructed with a buried perimeter edge drain system.  Portions of some driveways and yards were reconstructed to tie into the new street.  The project was designed and constructed by Jefferson County staff in 2007.


Bergen Parkway Pedestrian Flashers

The project consisted of the construction of pedestrian crossing improvements at the existing Buchanan Park and Buchanan Pond crossings on Bergen Parkway in Jefferson County, Colorado.  Improvements consisted of the installation of solar powered, wireless, crosswalk lights and flashers; crosswalk striping; and traffic signage.  The project provides for the improved safety of the students and other pedestrians to cross Bergen Parkway.   This project was 100% funded with Federal funds.

Jeffco Project No.  4-71-20-3584  CDOT Project No. SRTS R100-124 (15953)
Contract Bid:  $31,007.00   Final Cost:  $29,479.00
Start Date:  September 10, 2007  Finish Date:  October 31, 2007

Bergen Parkway Flashers

 Back to Top


South Kipling Pkwy Sidewalk - C-470 to W. Ute Avenue

Project Scope: 

Unlike the west side of Kipling Parkway between C-470 and West Ute Avenue, the east side of Kipling Parkway does not have a sidewalk.  Construction of an 8' wide sidewalk would greatly benefit the pedestrians who have worn a path in the grass between the Jefferson Village shopping center and the Chatfield Bluffs subdivision.  It would also address the citizens' concerns regarding the safety of pedestrians.  The $80,000 project, designed by County staff, is funded by the Road and Bridge Fund.

 S. Kipling before sidewalk construction
 

 

 

 

 

 

 

Progress Update:

The Road and Bridge construction crew has completed pot-holing for utility lines.  Weather permitting, the crew will grade the existing soil so the concrete sidewalk and ramps can be poured.  Minor repair of the existing irrigation system will be completed as part of this project.

Project Schedule:

Construction  Start:                    March, 2008                    End: April 2008

Back to Top


Lena Gulch at Isabell Street Channel Improvements
Project Scope:  In 1993, Jefferson County and Urban Drainage and Flood District (UDFCD) constructed a new culvert for Lena Gulch crossing Isabell Street.  Channel improvements to connect the culvert to the improved channel in Denver West were not constructed at that time because an easement could not be obtained.  Since that time, the downstream property has been sold and developed.
 Lena Gulch at Isabell Channel Improvements
 

 

 








 

During the development process a drainage easement for the Lena Gulch 100-year floodplain was obtained. The $440,000 project is funded equally be UDFCD and Jefferson County's General Fund.

 View project plans (pdf)! 

 
Progress Update:  The majority of the hauling has been completed.  Construction continues on the boulder-lined channel and on the other channel improvements.


Project Schedule:

Design               Start: May 2005                    End: August 2007
Construction       Start: January 2008               End: April 2008 
 


















 

Back to Top



Ken Caryl Avenue and Continental Divide Roadway Improvements
Project Scope:  Due to the expansive soils typically found in the Ken Caryl area of Jefferson County, a segment of Ken Caryl Avenue at Continental Drive Road required reconstruction.  Approximately 900 feet of Ken Caryl Avenue has been reconstructed, centered at the intersection of Ken Caryl Avenue and Continental Divide Road.  This project also included rotomilling, paving, and repairing curb and gutter, to various portions of Ken Caryl Avenue between Kipling Avenue and Continental Divide Road.  Ken Caryl and Continental Divide
The reconstructed portion of Ken Caryl Avenue was  lowered to increase visibility and improve the safety of the intersection.  To help prevent future heaving of the roadway, perimeter edge drains were installed with the project.  The intersection of Ken Caryl and and Continental Divide also received new handicap ramps and sidewalks.  This project was designed by Jefferson County staff.  Construction cost was approximately $610,000 and was funded by the Road and Bridge Fund.  
  

 

 

 











 

 
Progress Update: Construction Phasing Plans   
     
Project Schedule:     
Design  Start:  August 2007  End:  April 2008 
Construction  Start:  April 2008  End:  September 2008 
 

 


  

 
                                                             Back to Top



Belleview Avenue Widening, from Quincy Avenue to Simms Street 

Scope:  To raise Belleview to an arterial roadway standard, as identified in the Countywide Transportation Plan, the existing two-lane street will be widened to four through lanes.  Irrigated landscaping, sidewalks, and wood fencing are included in the plans by Muller Engineering.  The $15 million project is funded by the County Sales Tax Improvement District.

 
 Looking East from the Traffic Circle  Tree Placement East of C
  
  
Looking east from the traffic circle                Tree placement east of C-470

Progress Update
: October - 2008

The roadway widening project has been completed along West Belleview Avenue from Quincy Avenue to South Simms Street.  The County is currently having a contractor install landscaping features along the West Belleview Avenue corridor, which started in May and will continue through mid-October 2008.  

The landscaping work consisted of the installation of a computerized underground irrigation system, along with trees, shrubs, and pasture lawns throughout the site.  Approximately 100% of the work has been completed.

Construction Schedule (Roadway):  Start: September 2006   End: October 2008
Construction Schedule (Landscaping): Start: May 2008   End: October 2008

 


                                                 Back to Top 


JC 73, North Turkey Creek Road to Thimbleberry Lane

Project Scope:
 
Safety and capacity improvements were needed from North Turkey Creek Road to just north of the existing access to the Evergreen Professional Center. Plans were designed by Muller Engineering.  American Civil Constructors constructed the project.  The Evergreen/Conifer Traffic Impact Fee Fund paid for the improvements, estimated at $2.2 million.  Work began in March '08 and continued through October, 2008.

  JC  North JC  Roundabout
 

 

 

         

 

 

   JC-73 North - September 2008          Roundabout - September 2008

 The project included:

  • Roundabout GraphicA roundabout at JC 73/North Turkey Creek Road - Roundabout Link
  • The addition of four-foot paved, plus two-feet gravel shoulders in most areas
  • A two-way left-turn lane from the Evergreen South Cafe to Marshmerry Lane
  • A southbound left-turn lane at Marshmerry Lane
  • A northbound left-turn lane into Evergreen Professional Center
  • Fire station driveway improvements
  • Drainage improvements

View "For Construction" plan sheets

Progress Update: February 19, 2010

The Landscape Maintenance continues with the placement of topsoil, seeding, and the installation of the erosion blankets.  The maintenance includes the removal of trash, spraying of weeds, and mowing of the grass along the roadway shoulders.  The drainage inlet on North Turkey Creek Road has been modified and the drainage ditches repaired after the damages from the heavy rains.  The removal of sediment from the drainage ditches is now being done “as-needed”.  The contractor, American Civil Constructors, is now working on punch list items identified during the one year warranty inspection and should be completed in the spring.  Xcel Energy has completed the installation of the two remaining street lights at the roundabout.
Project Schedule:
Construction Start:                  March 2008            End:  September 2008
Landscape Maintenance Start:   October 2008         End:  December 2010

 

 

 

 

 

 

 

 

 

 

 

 


 




 

 

 

Back to Top


Bowles Sidewalk between Grant Ranch and Ames Street

Project Scope:  This project included the installation of sidewalk along the south side of Bowles Avenue between Grant Ranch and Ames Street.  The construction of a 5 ft. wide sidewalk will greatly benefit pedestrians since it will provide a connection between the Country Farms subdivision south of Bowles and the Villages at Raccoon Creek north of Bowles.  In addition, it provides a route to Blue Heron Elementary, which is located north of Bowles within the Villages at Raccoon Creek subdivision.  Area where Bowles Sidewalk will be constructed
 





 

 

 

 

 

Progress Update:  October 22, 2008

Sidewalk and grading is complete. The pedestrian button needs to be installed at Grant Ranch and Bowles. Once that is done the project will be complete.
 



 

 

Project Schedule:  
Design  Start:  August 2007  End:  December 2007 
Construction Start:  Summer 2008 End:  October 2008 

   

 

 

Back to Top


S. Oak Street Improvements - W. Bowles Avenue to W. Capri Avenue

Project Scope:  Alpers Farm Subdivision was platted in 2003.  At that time, Continental Homes, the developer, was required to pay the County $40,000 in lieu of constructing the half-street (east side) improvements on S. Oak Street from W. Bowles Avenue to approximately W. Capri Avenue.  The goal of this project is to construct curb, gutter, and sidewalk on the east side of S. Oak Street, and to add a right-turn lane at W. Bowles Avenue.  

 

 

 

The $100,000 project, designed by County staff, is funded by the Road & Bridge Fund. 
 

Progress Update:
Under construction.



Project Schedule:
 Construction  Start:  September 2008  End:  October 2008
 


Project Manager:
Contact Alecia Cope with Jefferson County at 303-271-8495 or acope@jeffco.us if you have questions or concerns.




Back to Top

 


Indiana Street Over Croke Canal

The existing Indiana Street Bridge over the Croke Canal just north of 55th Drive was given a very low bridge sufficiency rating under the Colorado Department of Transportation (CDOT) scoring system.  As a result this bridge will be replaced with a reinforced concrete box culvert. 

This project qualified for federal funding under the TEA-21 Act of the Federal Highway Administration (FHWA).  Up to 80% of funds used for design, right-of-way, and construction can be reimbursed to Jefferson County.

 Indiana Pre Construction-Looking North  Pre Construction - Looking Northeast
   
 Indiana Street at Croke Canal - During pre-construction - Looking north and northeast

 Indiana Post Construction-Looking North

 Indiana Post Construction - Looking Northeast
 
 Indiana Street at Croke Canal - Post-Construction - Looking north and northeast

Progress Update: November 14, 2008

Bridge construction on Indiana Street over Croke Canal has been completed.  Indiana Street between West 52nd Avenue and West 58th Avenue was opened to through traffic at noon on October 31, 2008.
The general contractor, KECI Colorado, Inc., completed the project approximately two months ahead of schedule. The newly constructed bridge was designed to be much safer for pedestrians, bicyclists, equestrian riders, and motorists. The traffic lanes are twelve feet in width, and there are now four foot wide paved shoulders on each side of the bridge.
In addition, there is new curb, gutter, and sidewalk as well as new "weathering steel" guardrails and bridge rail.  Jefferson County Division of Highways and Transportation would like to thank the area residents and businesses and the traveling public for their cooperation and patience during construction of the new bridge.

Project Schedule:

Construction:           Start: September 2, 2008            End: December 31, 2008

 

Project Manager:
Contact Gary Campbell with Jefferson County at 303-271-8495 or gcampbel@jeffco.us if you have questions or concerns.
 

 
Back to Top


2008 Traffic Signal Project

Coal Mine Drive and Coal Mine Avenue - A new traffic signal is scheduled to be constructed at the intersection of Coal Mine Avenue and Coal Mine Drive.  This location is at the main student parking lot for Dakota Ridge High School.  This traffic signal will cost $92,000 to install and construction will be completed by the beginning of September 2008.  Once installed, it will provide easier ingress to and egress from the Dakota Ridge High School student parking lot and the Dakota Ridge Apartments on the south side of Coal Mine Avenue. 

Project Schedule:  Completion: October 15, 2008    
Contractor:  Integrated Electric, Inc. - Contact - Tim Carpenter - 303.733.2028

 










 


Back to Top


Jefferson County Fairgrounds Drainageway "G" of Lena Gulch, Phase II

Purpose & Need:   
This project is to provide for the continuation of improvements within the Fairgrounds to reduce the downstream flooding caused by runoff flowing from Green Mountain.  During major rain storms, there is significant flooding of the 6th Avenue Frontage Road, Indiana Street and other properties between 6th Avenue and Colfax Avenue.
  Fairgrounds Detention - 1 Fairgrounds Detention - 2
 Fairgounds Detention - 3 Fairgounds Detention - 4

Jefferson County Fairgrounds - Drainage Way "G" of Lena Gulch
August 2009

Project Scope:
This project will design a regional detention pond to reduce peak runoff rates downstream of the Fairgrounds.  It is anticipated that drainage improvements for this project will cost in excess of $1,200,000. Design and construction costs will be shared equally between Jefferson County and Urban Drainage & Flood Control District (UDFCD).

Picture of the Jefferson County Fairgrounds Site Plan (pdf)

Updated aerial picture of the Fairgrounds (pdf)

Project Update: August 19, 2009
The new drainageway system and the off-line detention basin were completed in June.  A separate contract for landscaping was also completed in late July. The Jefferson County Division of Highways and Transportation and the Urban Drainage and Flood Control District would like to thank everyone for their cooperation during construction.
Project Schedule:
Construction  Started:  November 2008  End:  August 2009
Project Manager:
Contact Mark Winnen with Jefferson County at 303-271-8483 or mwinnen@jeffco.us if you have questions or concerns.
Back to Top


 

Jefferson County Government Center Roadway Improvements


Purpose and Need:

Work continues on the Jefferson County Government Center Roadway Improvements Project.  As the Regional Transportation District (RTD) advances toward Golden on the new West Corridor light rail extension project, Jefferson County is building a new roadway extension to Johnson Road to accommodate the increased traffic.  By early 2013 the West Corridor light rail system, parking structure and train station will be open to the public.  The new facility will be located just south of the Jefferson County Courts and Administration Building.  (Link to RTD's West Corridor web site at http://www.rtd-fastracks.com/wc_1.)

During the remainder of 2009, Jefferson County Parkway will be connected to Johnson Road by a new roadway segment near the south side of the County Jail.  This will allow employees and visitors a second access point to Johnson Road.  The current access from Johnson Road through the roundabout will remain open.  The Jefferson County Highways & Transportation Division will manage the roadway connection project.

 



 

 


 


 

                                                                                     

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 Mill Process

Milling Process

Jeffco Pkwy Final Paving

Jefferson County Parkway - Final Paving

Project Scope:

Jefferson County and the City of Golden teamed up to prepare the roadway design in 2008.  Both agencies will provide inspection and construction project management.  The improvements will include construction of a new roadway segment from Jefferson County Parkway to Johnson Road.  The road will have raised concrete medians, sidewalks, storm sewer, and two water quality ponds.  Portions of Johnson Road will have to be raised approximately three feet to complete the intersection grades.  The intersection will eventually be controlled by a traffic signal.  Some landscape work will be re-installed in 2009 and future plans call for added trees and shrubs in the connection road medians.

The project has been awarded to Concrete Express, Inc. for $1.28 million.  Jefferson County and the City of Golden will split the project costs on a 50/50 basis.  Work is anticipated to begin after April 6, 2009 and finish in early September 2009.

Project Update: 

Jefferson County Parkway
Since July, crews have installed new driveways at the delivery entrance and ballot drop off area, which are both now open.  All sidewalks on the project have been poured and are open for use.  RTD's bus stop has been moved back to the original shelter area.  Crews have finished the last stages of asphalt milling and paving.  They are currently installing trees and shrubs in the concrete medians, placing topsoil and seeding.
Final signing and roadway striping will be installed during the week of August 24th.  As the project wraps up, additional street lighting will be installed and new traffic signals will be placed at the intersection of Johnson Road / Jefferson County Parkway.  This new intersection will be STOP sign controlled until traffic volumes increase to warrant the signal operation.

FasTracks Light Rail Station - Denver Transit Construction Group (DTCG) crews began soil excavation behind the courthouse overflow parking lots and are transferring the material to a new parking lot across from the Sheriff's Office at Weimer Street.  Work is expected to continue for about one month.  The concrete trail by West 6th Avenue and an interior trail at Weimer Street will be temporarily closed to pedestrian and bicycle traffic until the construction is finished.

 Project Schedule:
 Week of April 6, 2009 Start Roadway Construction
 April 16-June 15, 2009 Phase I Construction Johnson Road Closure
 June 16 - Early September, 2009  Phase II Construction Jefferson County Parkway Partial Closure
September 2009 Finish Roadway Construction  

Project Manager: Contact John Suess at Jefferson County at (303) 271-8495 or jsuess@jeffco.us if you have questions or concerns.

For More Information:
See the full press release for more information.

Back to Top

 


NEAT Meadow Trail

Purpose and Need:


This project will construct an approximately half-mile long paved trail to complete the North Evergreen Activity Trails (NEAT) Meadow Trail which is the first piece of a larger NEAT Trail System that will connect local subdivisions, three public schools, the Buchanan Recreation Area, the Evergreen Fire & Rescue Department, and six shopping areas. NEAT is a trail system designed to provide safety, access, recreation and fitness throughout the community. 
   
                         Before                                           After (October 12, 2009)
NEAT Meadow Trail Before ImprovementsNeat Meadow Trail After sidewalk was installed

The purpose of the NEAT Meadow Trail is to provide trail access and fill in trail gaps between existing trail segments, and to provide a safe continuous trail between Evergreen Middle School and Broadmoor Drive. The trail will be constructed on property owned by the county, schools, a neighborhood homeowners' association, and a couple of private property owners.

                         Before                                                     After (July 28, 2009)
NEAT Meadow Trail Before sidewalk was installedNeat Meadow Trail after sidewalk in July, 2009

Trail planning was completed by the Highways & Transportation Division staff and the NEAT board and steering committee, with input from the Colorado Division of Wildlife's Wildlife District Manager, a Jefferson County (Jeffco) Environmental Specialist, Jeffco Historical Liaison, and a Safe Routes to School Coordinator.

Project Scope:

The trail will be a 6'-wide concrete trail with a maximum slope of 8%. It will incorporate a minor rock wall, culverts, ADA-compliant curb and gutter, re-seeding of disturbed areas, and erosion control measures. Trail design standards used include those from the American Association of State Highway and Transportation Official's (AASHTO) Guide for the Development of Bicycle Facilities, the Federal Highway Administration's Bicycle Lanes Versus Wide Curb Lanes, Traffic Controls for Bicycle Facilities, and AASHTO's Policy on Geometric Design.

The Road & Bridge Division will be constructing the trail. Funds for this project include a $200,000 grant awarded in April 2008 from Great Outdoors Colorado and donations to NEAT.

Project Update:
The Road & Bridge Division has completed the major construction tasks, including pouring the concrete trail, on the Bergen Pkwy portion of the project. Tasks remaining include: resetting the dowel fence, completing top soil placement, seeding the disturbed area, crimping & mulching or laying erosion control blanket on the seeded area, and maintaining the erosion control measures until the disturbed area has been revegetated to 70% of the original condition.
Project Schedule:
October 2009                           Trail construction complete
 
Project Manager:
Contact Alecia Cope at Jefferson County at (303)271-8456 or acope@jeffco.us if you have any questions or concerns.

 



 

 


 

 


 

 






















 

 

 

 

 

 

 

 

 

 

 

 

 




















Back to Top  

 

 

Last Modified: Feb 19, 2010 12:56 PM

Copyright © 2006-2009 - Jefferson County, Colorado. All rights reserved.
Login
Home