by Public Information
comments open from August 19 until September 7

As the summer winds down, work on the West Corridor continues to progress. By the end of summer, strands of rail will be welded along the guideway for placement at a later date.
Current and Ongoing Activities in Area 1 (Jeffco Government Center to Denver Federal Center):
>> The retaining wall at the Jeffco Government Center expands every day and what was once a hillside now resembles a concrete hedge. When the wall is completely constructed, the final finish will be applied to blend the structure into the existing landscape. You can watch the construction project on the campus of the Jefferson County Government Center live through our Media-on-Demand page. Just click the link at the top of the page.
>> Work is in full throttle on Ulysses Street, with retaining wall construction moving at a rapid pace. A new storm sewer system will also be built under Ulysses and the final activity will be rebuilding Ulysses Street to match back to 6th Avenue.
>> The 6th Avenue westbound off-ramp has been relocated to eastbound Colfax. The new ramp sits under the Colfax light rail bridge. The traffic configuration on Colfax is now final and future traffic impacts should be minimal.
>> There’s light at the end of the tunnel! Crews have excavated about 15 feet of the tunnel under I-70 and the approach walls are in place. Crews continue to work under I-70 to complete the excavation and install the final wall panels for the future light rail tunnel.
>> The concrete deck on the light rail bridge over Indiana Street is being poured in sections. To accommodate equipment and manpower, this will require lane closures on 6th Avenue and Indiana. Watch for updates on the latest closures related to this portion of the project. Eastbound and westbound traffic on 6th Avenue will be detoured off the highway at Indiana, but will be able to cross Indiana and get right back onto 6th Avenue. Once the entire deck is in place, crews will begin installing the emergency sidewalks, curbs and fencing.
>> Preliminary work on the Red Rocks passenger station has begun with electrical and communication conduits in place and stem walls taking shape.
Upcoming Activities
All activities in Area 1 will continue through the summer, as well as grading, slope reconstruction and sub-ballast installation. Construction of the parking garage at Jeffco could begin in early September.
To get the latest information on construction and road closures, connect to the West Corridor Web site.
Information contained in this post adapted from the FasTracks newsletter.

